A. Background :

Fire on 29.20.16 has rendered the Assembly Hall Block unsafe for use. Assembly Block compromises:

  1. Assembly Hall
  2. Staff Room
  3. Library
  4. Sewing Room
  5. Living Skills Workshop
  6. Music Room
  7. Counselling Room
  8. Surau
  9. Toilets
  10. Printing Room

B. Rebuilding will include :

  1. Administration & Classroom Block (4 storey) : RM3,551,795.00 (Estimate)

Construction to start                                          : December 2018

Expected to be completed                                 : December 2020*

  1. Multipurpose Hall Block (3 storey)  : RM4,675,596.40 (Estimate)

Construction to start                                          : December 2018

Expected to be completed                                 : December 2020

*Demolition of former Assembly Hall Block  : December 2017

D. Total Estimated Project Cost                 : RM 8,227,391.40

Lampiran

(a) Latarbelakang Pembinaan Semula Bangunan SMK St Teresa Kuching

Bangunan dewan SMK St Teresa telah dilanda musibah kebakaran pada 29 Oktober 2016. Kebakaran tersebut telah mengakibatkan kemusnahan keseluruhan dewan sekolah yang juga menempatkan Bilik Skim Pinjaman Buku Teks (SPBT) dan Bilik Siaraya di tingkat atas. Di tingkat bawah pula menempatkan Bilik Guru, Bilik Jahitan dan Bengkel Kemahiran Hidup, Bilik Kerja dan Fail Guru, Perpustakaan, Bilik Muzik, Surau, Bilik Bimbingan dan Kaunseling, Bilik Cetak, tandas guru dan dan tandas pelajar. Dengan itu, satu bangunan baharu yang merangkumi bilik-bilik tersebut perlu dibina.

Maklumat bilik-bilik yang akan dibina adalah seperti berikut :